Project Timeline
May 2012
- Stetson slate roof removed and repaired
- Stetson windows removed, replaced with temporary windows
- Pour elevated Level 2, Addition
June 2012
- Stetson chimneys replaced
- Form elevated slab, North Addition, Level 3
- Wood repair and refinish, Stetson, Level 1
July 2012
- Form elevated slab, South Addition, Level 4
- Reinstall windows, Stetson, West Elevation
August 2012
- Form elevated slab, North Addition, Level 4
September 2012
- Form elevated slab, South Addition, Level 5
- Start Facade, West and South Sides of Addition
October 2012
- Form elevated slab, North Addition, Level 5
- Stetson Weather Tight
November 2012
- Install Roof, South Addition
- Erect structural steel, North Addition, Level 6
December 2012
- Install masonry and slate wall system, West Elevation
- Install Roof, North Addition
January 2013
- Post Tension Slab Work Complete
- Start Facade, East and North Sides of Addition
April 2013
- Structural Topping Off of Addition Complete
- Exterior Facade Complete, Addition
May 2013
- Addition Weather Tight for Finishes
- Stetson Punchlist Complete
June 2013
- Stetson Commissioning Complete
September 2013
- Final Project Grading Complete
October 2013
- Addition Punchlist Complete
- Substantial Completion, Addition and Stetson
November 2013
- Certificate of Occupancy, Stetson and Addition
February 2014
- Substantial project completion
March 2014
- Begin Moving Furniture into Building
July 2014
- Move Collections into Library
August 2014