Project Timeline

May 2012

  • Stetson slate roof removed and repaired
  • Stetson windows removed, replaced with temporary windows
  • Pour elevated Level 2, Addition

June 2012

  • Stetson chimneys replaced
  • Form elevated slab, North Addition, Level 3
  • Wood repair and refinish, Stetson, Level 1

July 2012

  • Form elevated slab, South Addition, Level 4
  • Reinstall windows, Stetson, West Elevation

August 2012

  • Form elevated slab, North Addition, Level 4

September 2012

  • Form elevated slab, South Addition, Level 5
  • Start Facade, West and South Sides of Addition

October 2012

  • Form elevated slab, North Addition, Level 5
  • Stetson Weather Tight

November 2012

  • Install Roof, South Addition
  • Erect structural steel, North Addition, Level 6

December 2012

  • Install masonry and slate wall system, West Elevation
  • Install Roof, North Addition

January 2013

  • Post Tension Slab Work Complete
  • Start Facade, East and North Sides of Addition

April 2013

  • Structural Topping Off of Addition Complete
  • Exterior Facade Complete, Addition

May 2013

  • Addition Weather Tight for Finishes
  • Stetson Punchlist Complete

June 2013

  • Stetson Commissioning Complete

September 2013

  • Final Project Grading Complete

October 2013

  • Addition Punchlist Complete
  • Substantial Completion, Addition and Stetson

November 2013

  • Certificate of Occupancy, Stetson and Addition

February 2014

  • Substantial project completion

March 2014

  • Begin Moving Furniture into Building

July 2014

  • Move Collections into Library

August 2014

  • New Sawyer Library opens